Whether you’re facing challenges or looking for tailored solutions, our team is here to help. Get in touch with us today and take the next step towards securing your business’s future.
TL;DR: On South African construction projects, the performance guarantee is rarely the only security a contractor has to provide. An advance payment guarantee lets the contractor receive money up front and reduces as that money is repaid. Retention is money held back from each payment certificate until completion and the end of the defects period, and a guarantee can sometimes be given in its place. Bid or tender security, where a tender asks for it, backs the bidder’s promise to sign the contract. The CIDB caps how much security public sector employers can demand, and the wording of each guarantee decides when it can be called.
On a R20 million building contract, a 5% deduction from every payment certificate means up to R1 million of the contractor’s own money sits with the employer until practical completion. Add an advance payment that has to be secured, and a construction guarantee on top, and the security package can tie up more working capital than the contractor’s margin on the job. Understanding each piece, and what can replace it, is one of the most practical ways to protect cash flow on a project.
Our guide to performance guarantees covers the main guarantee. This article explains the other three you are most likely to meet: advance payment guarantees, retention and retention guarantees, and bid security. It is general information. The contract and the guarantee wording on your project will always govern.

An employer takes two financial risks when it appoints a contractor: that the contractor will not finish the work properly, and that money paid in advance will not be recovered. South African standard contracts deal with this through a combination of guarantees and money held back.
Under the JBCC Principal Building Agreement (edition 6.2), for example, the contractor chooses within 15 working days of tender acceptance between two forms of security for construction:
Where an advance payment is agreed, the JBCC requires a separate guarantee for advance payment. If the contractor does not provide the guarantee for construction at all, the employer may withhold up to 10% of the contract sum instead, reducing to 2.5% at practical completion. Other contracts, including the GCC and NEC suites, use different mechanics for the same purpose.
An advance payment helps a contractor mobilise, buy materials or order long-lead plant before the first payment certificate. The employer protects that money with an advance payment guarantee, which allows it to recover the unrepaid balance if the contractor fails to perform.
Ask for the reduction mechanism to be clear in the wording, so that the guarantee, and the guarantor’s exposure, falls as repayments are certified rather than staying at the full advance until the end of the project.
Retention is a percentage withheld from each interim payment to give the employer security for completion and for defects that appear after handover. It is cash the contractor has earned but cannot yet use.
SAICE published GCC 2025, a new edition of the General Conditions of Contract for Construction Works, in September 2025, including updated retention provisions. If your next project uses GCC 2025 rather than GCC 2015, check the security and retention clauses rather than assuming they are unchanged.
Some tenders ask bidders to provide bid security, also called a bid bond or tender guarantee. It protects the employer if the preferred bidder withdraws its tender during the validity period or refuses to sign the contract and provide the required performance security.
The amount and form are set in the tender documents, so read them early. A bid guarantee usually expires shortly after the contract is awarded and replaced by the performance and advance payment guarantees. Because bid security is needed before the bid is submitted, the time to arrange guarantee facilities is before tender season, not on the closing date.
For public sector construction, the CIDB Standard for Uniformity (Board Notice 423 of 2019) sets limits on security:
The CIDB published a draft second edition of the Standard for comment in July 2026 (Board Notice 963 of 2026). The draft keeps the same retention caps, says performance bonds should not be required for service, professional service and supply contracts, and allows advance payments only against a suitable advance payment bond. It is not yet final, so check the version in force when you tender.
South African courts treat construction guarantees as independent of the building contract. In Lombard Insurance v Landmark Holdings [2009] ZASCA 71, the Supreme Court of Appeal held that a guarantee payable on the happening of a stated event is like a letter of credit: the guarantor must pay when the demand complies with the guarantee, and disputes under the building contract are no reason to refuse. The only exception is fraud by the beneficiary. The court confirmed the same approach in later cases, including Coface v East London Own Haven [2013] ZASCA 202.
Not every guarantee is on demand, though. In Minister of Transport and Public Works, Western Cape v Zanbuild Construction [2011] ZASCA 10, the court explained that a conditional guarantee requires the beneficiary to allege, and sometimes prove, the contractor’s liability, while an on-demand guarantee does not. Which kind you have depends on the wording, not the title. In Aveng Strabag v SANRAL [2020] ZASCA 146, a contractor’s attempt to stop SANRAL calling a performance guarantee on the Mtentu Bridge project pending arbitration failed, because the contract allowed payment before the dispute was decided.
For contractors, the practical point is simple. Once an on-demand guarantee is issued, you will have little room to stop a call, so negotiate the call conditions, expiry date and reduction mechanism before you sign. Our article on what is hiding in your construction contract covers other clauses to check.
Guarantees can be issued by a bank or by a registered insurer, and the CIDB Standard recognises both. In 2026 the High Court in Elasah Risk Consultants v National Credit Regulator held that construction guarantees which transfer risk are guarantee policies under the Insurance Act 18 of 2017, so that only licensed insurers may issue them. It is a High Court judgment and may yet be considered on appeal, but it is a reminder to check that whoever issues your guarantee is properly licensed, because an employer can reject a guarantee from an unacceptable institution.
Some contractors prefer insurance guarantees so that their banking facilities remain available for working capital. Our guide to guarantees as credit instruments explains how a guarantee facility with an insurer is structured and what information an insurer will ask for.
Berkley Risk arranges construction guarantees through licensed insurers. See our bond and guarantee insurance page, or our local pages for the Western Cape, Sandton, Durban and Limpopo. Contractors working on the North Coast or in Cape Town can also see our North Coast and Cape Town contractor project pages, and our construction and engineering insurance page covers the rest of a project programme.
It is a guarantee that secures money paid to a contractor before work is done, such as a mobilisation payment. If the contractor fails to perform, the employer can call on it to recover the unrepaid balance. It usually reduces as the advance is repaid through payment certificates.
Retention is a percentage withheld from each payment certificate as security for completion and defects. It is released in stages, typically at completion and after the defects liability period. For public sector work, the CIDB caps it at 10% of any amount due and 5% of the contract price in total where a guarantee has also been provided.
Often, yes, where the contract allows it. Under the JBCC, for example, choosing the variable construction guarantee of 10% avoids the 5% payment reduction that applies with the fixed guarantee.
A bid bond, or tender guarantee, secures a bidder’s promise not to withdraw its tender during the validity period and to sign the contract and provide the required guarantees if it is awarded the work. The amount and form are set in the tender documents.
If the guarantee is on demand, generally yes. South African courts treat on-demand guarantees as independent of the building contract and will usually only stop a call for fraud by the beneficiary. Conditional guarantees are different and depend on their wording.
Berkley Risk (Pty) Limited (Registration Number 2017/412000/07)
Authorised Financial Services Provider under the Financial Advisory and Intermediary Services Act No 37 of 2002 – FSP#54407